Home about us Activities Our Projects Safety Certificates contact us

::: Contracts History :::

Contract/Location

Contractor

Duration /Year

Scope of Work

South Power Station / Baghdad

GE International Inc.

2 months
2005

Testing and commissioning of 132kV outdoor switchyard, 6.6 switchgear and power transformers.

Rasafa Area/Baghdad

Schneider Electric

14 months

Supervision of the erection of 14 no. 33/11 kV substations including civil and mechanical works.

Daura Power Station/Baghdad

ABB

6 months

132 kV switch yard including civil structure works, installation of 14 bays comprising C.B's, CT's, VT's, surge arresters with all controls then testing and commissioning.

Adamiya District Elect. Network Rehabilitation / Baghdad

Directorate of Baghdad Electricity

18 months
2003

Survey , design, procurement, installation and commissioning of a new underground network to serve almost 14,000 consumers using kiosk S/S ,HT cables ,LT cables and twisted cables. After completion of the design, the contract had been terminated because of the 2003 war.

Daura Power Station/Baghdad

Bechtel Int. Sys. Inc.

3 months
2003

Rehabilitation and testing of a 50MVA transformer which was damaged because of penetrated fragments.

Adamiya 132/33kV Substation /Baghdad

Ministry of Industry

3 months
2002

Erection of out door steel structure and busbars, installation of 33kV and control cables, then commissioning of 132kV (10 bays) substation.

Qanal & Ataifiya WTP/Baghdad

Ministry of Industry

4 months
2002

Provisioning of equipment and rehabilitation of several water treatment plants and pumping stations.

Sheik Omer Clinic/Baghdad

United Nation (UNOPS)

5 months
2000

Rehabilitation of civil, electrical and airconditioning system.

Taj Sheba Hotel /Yemen

Waycon Company

8 months
1998

Maintenance , provisioning and erection of all electro-mechanical system of the 5 star hotel.

UN Headquarters/Baghdad

United Nation

36 months
1997

Electro-mechanical maintenance contract.

Taiz-Aden Power Llink /Yemen

Ansoldo Company

36 months
1996

With the cooperation of Ansoldo Co. of Italy ,Al-noor completed Taiz -Aden power link project of 400/132/33/11kV GIS and conventional type distribution S/S.

Sharq Dijla Transmission Line /Baghdad

Ministry of Industry

12 months
1995

Installation of 33kV TL, 250-1000kVA kiosks complete with LT distribution network .

Rafidain Bank/ Kerbala Governorate

Ministry of Finance

12 months 1993

Design and construction of 4 story building including basement.

132/33/11 kV Substation /Diyala Governorate

Ministry of Industry

7 months
1989

Erection and commissioning of 2x63MVA capacity substation.

Copyright � 2008 Al-Noor Contracting Company International Ltd. (NC)
Powered & Designed by Infinity Stamp Technology